You need to ensure that you can view only the tasks on your projects critical path. What should you do?
A.
On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box.
B.
View the projects Gantt chart and apply the Critical group.
C.
View the project’s Gantt chart and apply the Critical filter.
D.
On the Advanced tab of the Project 2010 options, modify the Tasks are critical if slack is less than or equal to option.