Your organization uses Project Professional 2013 and records actual hours worked on the project.
You manage a small e-commerce website implementation project. One of your testers asks for
assistance in completing a critical task, and you find two additional testing resources that can assist
with executing the critical test cases. The total estimated work for the effort-driven task is 100
hours. The original testing resource, Resource1, completes 25 hours of work on the task. You need
to add Resource2 and Resource3 to the task and split the remaining hours across all three resources
now working on the task. Which two actions should you perform? (Each correct answer presents
part of the solution. Choose two.)
A.
Open the Task Form and format it to show Work Details. Enter 25 hours of actual work for
Resource1. Then save the changes.
B.
Open the Task Form and format it to show Work Details. Enter 75 hours of remaining work for the
assigned resource. Then save the changes.
C.
Assign Resource2 and Resource3 to the task. Then save the changes.
D.
Open the Task Form and format it to show Work Details. Enter 33.33 hours of work for each
resource. Then save the changes.