You need to ensure that all tasks are assigned to resources

Your organization uses Microsoft Project 2013. You are finalizing the Project Schedule for a very
complex project with over 100 resources. You need to ensure that all tasks are assigned to
resources. What should you do?

Your organization uses Microsoft Project 2013. You are finalizing the Project Schedule for a very
complex project with over 100 resources. You need to ensure that all tasks are assigned to
resources. What should you do?

A.
Use Task Usage view and look for Unassigned tasks.

B.
Use Resource Graph view and look for the Unassigned resource name.

C.
Use Resource Usage view and look for the Unassigned resource name.

D.
Use Resource Sheet view and look for Unassigned tasks.



Leave a Reply 0

Your email address will not be published. Required fields are marked *