You need to let the resource know how the Work will be affected

Your company uses Project Professional 2013. You are setting up a preliminary schedule by using
manually scheduled tasks. You create a task with no duration, start, or finish date, and then you
assign a resource. Later, you enter a duration of three days for that task. You need to let the
resource know how the Work will be affected. What should you say?

Your company uses Project Professional 2013. You are setting up a preliminary schedule by using
manually scheduled tasks. You create a task with no duration, start, or finish date, and then you
assign a resource. Later, you enter a duration of three days for that task. You need to let the
resource know how the Work will be affected. What should you say?

A.
Work will increase to 24 hours.

B.
Work will remain at 0 hours.

C.
Work will increase to 16 hours.

D.
Work will remain at 8 hours.