You are a project manager who uses Project Standard 2013. You are creating a preliminary project
schedule and are estimating the number of resources required prior to finalizing the schedule. You
do not have named resources to complete the tasks, but you know the resource roles that are
necessary. One of the roles needed is architect. You need to estimate how many architect hours are
required to complete the work. What should you do?
A.
Add a Material Resource named architect.
B.
Add a Budget Resource named architect.
C.
Add a Work Resource named architect,
D.
Add a Cost Resource named architect.