You are a program manager who uses Project Professional 2013. You manage a portfolio of projects
for a large point of sale implementation. All of your project managers have created individual project
schedules. You discover that you have resource constraints since multiple resources are working on
multiple projects. You need visibility into resources across all projects so that you can most
efficiently manage the resources and their availability. What should you do?
A.
Create a shared resource pool and send the location to each project manager. Open the individual
project and the resource pool. From the individual project, select Resource Pool, Share Resources,
and choose Use Resources.
B.
Create a shared resource pool and send the location to each Project Manager. Open the individual
project, select Resource Pool, Share Resources, and choose Use Resources.
C.
Create a master resource list and send it to each project manager. Open the individual project and
copy and paste it into the Resource Sheet.
D.
Create a master resource list and send it to each project manager. Open the individual project,
select Team Planner, and add the resources.