DRAG DROP
Your company uses Project Professional 2013. You are a program manager in charge of a multiprogram software integration project. The project is scheduled from January 1, 2012-August 3, 2013.
You have a consultant resource that charges a different rate based on each task completed. Tasks 1
through 9 are billed at a rate of $150.00 per hour. Tasks 10 through 20 are billed at a rate of $175.00
per hour. You need to set up your schedule to ensure that the correct resource rate is associated
with the correct tasks. Which two actions should you perform in sequence? (To answer, move the
appropriate two actions from the list of actions to the answer area and arrange them in the correct
order.)