you need to set the task type before adding the resources

You are a project manager for a software development company. You use Project Professional 2013.
You manage an integration project, and you discover that you need to add additional resources to
the integration tasks in order to meet your development complete milestone date. The project is
behind schedule, so you must shorten the duration of the integration development work. You
identify two additional resources to work on the integration task. When you add these resources,
your task now shows it will complete three days ahead of schedule, which leaves a contingency
window for issues that may arise. In order to shorten the duration of the task when the resources
are added, you need to set the task type before adding the resources. What should you do?

You are a project manager for a software development company. You use Project Professional 2013.
You manage an integration project, and you discover that you need to add additional resources to
the integration tasks in order to meet your development complete milestone date. The project is
behind schedule, so you must shorten the duration of the integration development work. You
identify two additional resources to work on the integration task. When you add these resources,
your task now shows it will complete three days ahead of schedule, which leaves a contingency
window for issues that may arise. In order to shorten the duration of the task when the resources
are added, you need to set the task type before adding the resources. What should you do?

A.
Use an automatically scheduled task and set the task type to fixed duration.

B.
Use a manually scheduled task and set the task type to fixed work.

C.
Use an automatically scheduled task and set the task type to fixed work.

D.
Use a manually scheduled task and set the task type to fixed duration.