You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreedupon working days and hours

You are a senior project manager, and your organization uses Project Standard 2013. You are
managing a large ERP project with both part-time and full-time resources. The part-time resources
have strict contractual limitations regarding working days and hourly availability. You need to make

sure the tasks for your part-time resources are only scheduled in the calendar during their agreedupon working days and hours. What should you do?

You are a senior project manager, and your organization uses Project Standard 2013. You are
managing a large ERP project with both part-time and full-time resources. The part-time resources
have strict contractual limitations regarding working days and hourly availability. You need to make

sure the tasks for your part-time resources are only scheduled in the calendar during their agreedupon working days and hours. What should you do?

A.
Change the part-time resources’ tasks to manually scheduled to ensure the dates do not go past
the agreed-upon terms of their contract.

B.
Enter the availability start and end dates for each resource and change the percent of units to the
agreed-upon amount in their contract.

C.
Enter the availability start and end dates for each resource and change the working time for each
resource to only include days and hours agreed upon in their contract.

D.
Change the part-time resources’ units to the percentage they are available and set task
constraints to must finish on to ensure the dates do not go past the agreed-upon terms of their
contract.