Which two actions should you perform?

Your organization uses Project Professional 2013. A senior stakeholder in a project asks you to
determine when a task is over budget by comparing the baseline cost of a task to the cost.
Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost
is greater than the cost. You write a formula to display the indicator, but it only displays for normal
tasks and not for summary tasks. You need to make the indicator display for summary tasks. Which
two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

Your organization uses Project Professional 2013. A senior stakeholder in a project asks you to
determine when a task is over budget by comparing the baseline cost of a task to the cost.
Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost
is greater than the cost. You write a formula to display the indicator, but it only displays for normal
tasks and not for summary tasks. You need to make the indicator display for summary tasks. Which
two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

A.
Within the Custom Field, set Calculation for task and group summary rows to Use Formula.

B.
Within the Custom Field, set Calculation for task and group summary rows to Maximum.

C.
Within the Graphical Indicators dialog box, check the Import Indicator Criteria button.

D.
Within the Graphical Indicators dialog box, check Summary rows inherit criteria from
nonsummary row.