You are a project manager, and you successfully complete a server consolidation project for one of
your data centers. You use Project Standard 2013 to plan and track the work. Your manager wants
you to begin similar projects on two other data centers. You need to create a template based on the
plan you used to manage the first data center consolidation project. You need to ensure that the
template has all baseline and actual data values removed. What should you do?
A.
Within Microsoft Windows Explorer, create a copy of the original project plan and rename the file
type from .mpp to .mpt.
B.
Open the plan and use the Move Project button to set the start date to the start of the new
project. Save the project file as Template.mpp.
C.
Open the plan and reset the percent complete for each task to 0. Save the file as Template.mpp.
D.
Open the plan and save the plan as a Project Template.
E.
Open the plan, and copy and paste all of the task information into a new plan. Save the plan as a
Project Template.