You need to set up a method that allows you to pick the renewal month for each resource

You are a resource manager who uses Project Standard 2013. You manage all of your resources in a
single plan, which acts as a Shared Resource Pool for other projects in your organization. Each
resource needs to pass an annual exam in order to work on construction sites. You need to set up a
method that allows you to pick the renewal month for each resource. What should you do?

You are a resource manager who uses Project Standard 2013. You manage all of your resources in a
single plan, which acts as a Shared Resource Pool for other projects in your organization. Each
resource needs to pass an annual exam in order to work on construction sites. You need to set up a
method that allows you to pick the renewal month for each resource. What should you do?

A.
Rename the Resource Text1 Custom field to Exam Expiration Date. Enter the month when the
exam expires. Select the correct expiration date for each resource.

B.
Use the Organizer to copy the Resource Finish1 Custom field from the Global.mpt. Select the
correct expiration date for each resource.

C.
Rename the Resource Date1 Custom field to Exam Expiration Date. Create a Lookup table with
values containing the last date of each month. Select the correct expiration date for each exam.

D.
Rename the Resource Month1 Custom field to Exam Expiration Date. Create a Lookup table with
monthly values. Select the correct expiration month for each exam.

E.
Rename the Resource Flag1 Custom field to Exam Expired Date. Enter the expiration dates into a
Lookup table. Select the correct expiration date for each resource.