Which two steps should you perform?

You are a project manager who uses Project Standard 2013, and your task list includes a flag field
that indicates, with Yes or No, if a non-summary task represents a physical deliverable. Your project
involves several tasks marked as deliverables, and management requires you to track how many
deliverables are completed. The deliverable is considered completed when the Percent complete
field is 100%. You need to create a formula to calculate the total number of deliverables that are
completed. Which two steps should you perform? (Each correct answer presents part of the
solution. Choose two.)

You are a project manager who uses Project Standard 2013, and your task list includes a flag field
that indicates, with Yes or No, if a non-summary task represents a physical deliverable. Your project
involves several tasks marked as deliverables, and management requires you to track how many
deliverables are completed. The deliverable is considered completed when the Percent complete
field is 100%. You need to create a formula to calculate the total number of deliverables that are
completed. Which two steps should you perform? (Each correct answer presents part of the
solution. Choose two.)

A.
Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,1,0).

B.
Set Calculation for tasks and summary groups to Sum.

C.
Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,0,1).

D.
Set Calculation for tasks and summary groups to Count All.