You need to reflect the closure within your schedule

You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to
update your project to reflect your organization’s scheduled two-week closure. You need to reflect
the closure within your schedule. What should you do?

You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to
update your project to reflect your organization’s scheduled two-week closure. You need to reflect
the closure within your schedule. What should you do?

A.
Create a resource and specify non-working days for the resource which reflect the closure. Assign
this resource to each task.

B.
Open the Project Calendar and modify the default work week by setting the dates as non-working
time.

C.
Create a new calendar and assign this to the tasks that are scheduled over the period of closure.

D.
Open the Project Calendar and enter the planned closure in the Exceptions tab.