You need to use the Baseline2 fields to calculate Variance at Completion (VAC)

You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to
calculate Variance at Completion (VAC). You have already set Baseline2. What should you do?

You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to
calculate Variance at Completion (VAC). You have already set Baseline2. What should you do?

A.
Enter physical percent complete for the tasks that have actual values. Set the Baseline to the
Baseline2, and reschedule uncompleted work based on the status date.

B.
Change the Earned Value method to Baseline2 in the Task Information Form. Enter tracking data,
and view the VAC on the Earned Value table.

C.
Change the Baseline for Earned Value calculation option to Baseline2, and reschedule
uncompleted work based on the status date.

D.
Go to the Earned Value table and insert the Baseline2 column. Recalculate the project.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


RD

RD

Why would you need to reschedule uncompleted work based on status date (answer c)?