You need to resolve the negative Total Slack values

You are a project manager who uses Project Professional 2013. When viewing the critical path, you
notice that there are some inconsistencies. To investigate the status of the critical path, you insert
the Total Slack column into a task table. You discover that many of the tasks have negative Total
Slack values. You need to resolve the negative Total Slack values. What should you do?

You are a project manager who uses Project Professional 2013. When viewing the critical path, you
notice that there are some inconsistencies. To investigate the status of the critical path, you insert
the Total Slack column into a task table. You discover that many of the tasks have negative Total
Slack values. You need to resolve the negative Total Slack values. What should you do?

A.
Remove lag time from task relationships.

B.
Remove as many constraints as possible.

C.
Re-assign resources that have more availability at the time of the negative slack.

D.
Remove lead time from the task relationships.