What should you do?

You manage a project by using Project Professional 2013. The work variance for a task is 48 hours.
The remaining work is 25 hours. The work for this task has been completed. You need the work
variance to be adjusted to reflect what has occurred during the performance of the task. What
should you do?

You manage a project by using Project Professional 2013. The work variance for a task is 48 hours.
The remaining work is 25 hours. The work for this task has been completed. You need the work
variance to be adjusted to reflect what has occurred during the performance of the task. What
should you do?

A.
Adjust the value in the Baseline Work column.

B.
Enter a 0 in the remaining Duration column.

C.
Adjust the value in the Work Variance column.

D.
Mark the task inactive.



Leave a Reply 0

Your email address will not be published. Required fields are marked *