You manage a project and use Project Professional 2013 to track your project schedule. One of
several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at 50% of their
availability. The resource asks to start the task three days later than planned because of a scheduling
conflict. The schedule change is approved. You need to make the adjustment to the resource
assignment to accommodate this request without affecting the other resources assigned to the task.
What should you do?
A.
Use the Resource Usage view and add duration to the assignment to extend the deadline three
days.
B.
Use the Gantt Chart view tracking table and add a Start no earlier than constraint to the task.
C.
Use the Task Form formatted to show Work Details and add a three-day delay to the assignment
for the resource.
D.
Use the Task Form formatted to show Schedule Details and add a three-day delay to the
assignment for the resource.