While creating a schedule with Project Professional 2013, you notice that there is a three-day
duration on the Database Design task. After working for only two days, the resource performing the
task reports two days of work and notifies you that the task is finished. You need to update the
schedule with this information. What should you do?
A.
Reschedule uncompleted work for the project schedule.
B.
Add two days of actual duration and change the remaining duration for the task to zero.
C.
Update the task to show 100% completion on the ribbon bar.
D.
Enter a status date for the task.