You need to resolve this problem

You manage a project for an organization that uses Project Professional 2013. You reset the baseline
for some selected tasks. After the baseline has been updated with the new values, you realize that
some of the summary baseline duration values are not correct. You need to resolve this problem.
What should you do?

You manage a project for an organization that uses Project Professional 2013. You reset the baseline
for some selected tasks. After the baseline has been updated with the new values, you realize that
some of the summary baseline duration values are not correct. You need to resolve this problem.
What should you do?

A.
Update the summary tasks manually with the new duration values.

B.
Change all task durations to the same denomination values, such as days, weeks, or months.

C.
Reset the baseline for the selected tasks and select the Roll up baselines to all summary tasks
option.

D.
Reset the summary tasks to manual scheduling.