You need to set up a dependency between these two tasks

Your company uses Project Professional 2013. You are scheduling two tasks. One task is named Test
Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to
start three working days after the finish date of the Create Solution Test Plan task. You need to set
up a dependency between these two tasks. What should you do?

Your company uses Project Professional 2013. You are scheduling two tasks. One task is named Test
Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to
start three working days after the finish date of the Create Solution Test Plan task. You need to set
up a dependency between these two tasks. What should you do?

A.
Create a Start to Start predecessor relationship from the Create Solution Test Plan task to the Test
Solution task. Set a lead time of three days.

B.
Create a Start to Start predecessor relationship from the Test Solution task to the Create Solution
Test Plan task. Set a lead time of three days.

C.
Create a Finish to Start predecessor relationship from the Test Solution task to the Create Solution
Test Plan task. Set a lag time of three days.

D.
Create a Finish to Start predecessor relationship from the Create Solution Test Plan task to the
Test Solution task. Set a lag time of three days.