You need to display the critical path for the entire program instead of each independent project

Your company uses Project Professional 2013. You are a program manager who has a master project
created for your program. Currently you are seeing the critical path for each independent project in
the master project. As a program manager, you want to ensure the resources are properly applied to
successfully complete the program. You need to display the critical path for the entire program
instead of each independent project. What should you do?

Your company uses Project Professional 2013. You are a program manager who has a master project
created for your program. Currently you are seeing the critical path for each independent project in
the master project. As a program manager, you want to ensure the resources are properly applied to
successfully complete the program. You need to display the critical path for the entire program
instead of each independent project. What should you do?

A.
Turn on Inserted projects are calculated like summary tasks in the Schedule section of Project
Options.

B.
Turn on Calculate multiple critical paths in the Advanced section of Project Options.

C.
Insert the Critical field, and change the values to Yes for the non-critical tasks.

D.
Double-click the inserted project summary task and uncheck Roll Up.



Leave a Reply 0

Your email address will not be published. Required fields are marked *