Your organization uses Project Professional 2013. A senior stakeholder informs you that your project
start date is delayed and gives you a new start date. You need to change the project start date
without adding constraints. What are three possible ways to achieve this goal? (Each correct answer
presents a complete solution. Choose three.)
A.
Modify the Start Date field in project information to the new date.
B.
Use Move Project to move the project to the new start date.
C.
Enter the new start date for all tasks without predecessors.
D.
Use Update Project and set a new start date.
E.
Set a new project status date and then set the baseline.