You are using Project Standard 2013. Management wants to see an overview of your project that
shows the overall start and finish dates, total duration, and the name of the project. They want to
see this information in a simple layout that does not include task details. You need to show one line
item that displays all the requested information in the Gantt view. What should you do?
A.
Apply the Top Level Tasks filter.
B.
On the format ribbon, check the box next to Project Summary Task.
C.
Apply the default Summary Tasks filter.
D.
On the format ribbon, check the box next to Summary Tasks.
not right, should be B.
https://support.office.com/en-us/article/Show-the-project-summary-task-5F29729B-5B22-4E75-A8AB-C69F2AA17573?ui=en-US&rs=en-US&ad=US