You need to maintain this priority throughout the execution of the project

Your company uses Project Professional 2013. You have two projects, Project 1 and Project 2, as well
as a resource pool to contain all of the resources. You use resource leveling and want to prioritize
the projects so that Project 1 is the highest priority project and gets all the required resource
availability first. Project 2 then gets resources as they become available from Project 1. You need to
maintain this priority throughout the execution of the project. What should you do?

Your company uses Project Professional 2013. You have two projects, Project 1 and Project 2, as well
as a resource pool to contain all of the resources. You use resource leveling and want to prioritize
the projects so that Project 1 is the highest priority project and gets all the required resource
availability first. Project 2 then gets resources as they become available from Project 1. You need to
maintain this priority throughout the execution of the project. What should you do?

A.
Set resource leveling to prioritize by project, priority, and standard.

B.
Make sure the resource pool is configured to list Project 1 first.

C.
Level Project 1 first, and then level Project 2.

D.
Set Project Priority higher for Project 1, and then set resource leveling to level by priority,
standard.