You need to determine the cause of the wavy red line

Your organization uses Project Professional 2013. You are setting up a preliminary schedule by using
manually scheduled tasks. As you build the task breakdown, you notice a potential scheduling
problem indicated by a wavy red line under the finish date of a detail task. You need to determine
the cause of the wavy red line. What should you do?

Your organization uses Project Professional 2013. You are setting up a preliminary schedule by using
manually scheduled tasks. As you build the task breakdown, you notice a potential scheduling
problem indicated by a wavy red line under the finish date of a detail task. You need to determine
the cause of the wavy red line. What should you do?

A.
Evaluate the task to determine if there is a deadline.

B.
Insert the Constraint Type field and view the task constraints.

C.
Evaluate the task by using the Task Inspector.

D.
View the Resource Sheet to see if you have overallocated resources.