You need to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience

You are a project manager who uses Project Professional 2013. You have worked on a project for
four years and have created a very detailed project plan in Project Professional 2013. You use
milestones as key deliverables, and you use summary tasks as phases. Your company requests a
presentation of the key deliverables for each phase of your project plan in a simple and consolidated
view that fits in one Microsoft PowerPoint slide. You need to ensure that phases and key
deliverables are clearly shown in the timeline and are not confusing to the audience. What should
you do?

You are a project manager who uses Project Professional 2013. You have worked on a project for
four years and have created a very detailed project plan in Project Professional 2013. You use
milestones as key deliverables, and you use summary tasks as phases. Your company requests a
presentation of the key deliverables for each phase of your project plan in a simple and consolidated
view that fits in one Microsoft PowerPoint slide. You need to ensure that phases and key
deliverables are clearly shown in the timeline and are not confusing to the audience. What should
you do?

A.
Create a new Timeline view from existing tasks in your project plan. Drag the timeline into a blank
PowerPoint slide.

B.
Create a new Timeline view that automatically shows milestones for each stage of your project.
Copy the full-size timeline and paste to your PowerPoint slide.

C.
Add all summary tasks to your timeline. Project Professional 2013 will automatically recognize and
add all milestones on each stage to your Timeline view. Copy the full-size timeline and paste to the
PowerPoint slide.

D.
Add all summary tasks to your timeline. Add all milestones to your timeline. Copy the full-size
timeline and paste to your PowerPoint slide.