You are a project manager who uses Project Professional 2013. You have created a project which
involves three other colleagues who are also using Project Professional 2013. You and your
colleagues are over budget and cannot spend any more money on this project. To ensure that the
latest version of the project file is always the one being used, you need to save, share, and sync this
project plan File among your colleagues without using email. What should you do?
A.
Save and sync your project by using SkyDrive.
B.
Save and sync selected tasks in the project by using SkyDrive.
C.
Save and sync your project to a shared Microsoft Excel file.
D.
Save and sync selected tasks in your Microsoft SharePoint Tasks List.