You are a project manager for a software development company that uses Project Professional 2013.
For managing projects, your company has its own specialized processes, all of which you are familiar
with, except for the reporting processes. Additionally, your company’s status reports of project
progress are based on Work and Cumulative Work. Thirty minutes before a meeting is scheduled to
begin, the president of your company asks you to present the status report at the meeting. You need
the report to show all project tasks, resources assigned, and their respective Work and Cumulative
Work on a monthly basis. What should you do?
A.
Select the Gantt Chart view that has all project tasks and resources assigned. Click Add New
Column to add Work and Cumulative Work. Go to the Gantt chart and adjust the timescale by
zooming in or out to fit the monthly basis.
B.
Select the Gantt Chart view that has all project tasks and resources assigned. Right-click on the
Gantt chart, selecting Work and Cumulative Work. Adjust the timescale by zooming in or out to fit
the monthly basis.
C.
Select the Task Usage view that has all project tasks and resources assigned. Right-click the Details
table, selecting Work and Cumulative Work. Adjust the timescale by zooming in or out to fit the
monthly basis.
D.
Select the Network Diagram View. Choose Format Box Styles and add Cumulative Work to the
Critical Task Box style.