You are a Project Manager who uses Project Professional 2013. You manage a critical project, which
is synchronized with a Microsoft SharePoint Task List. One of your team members has changed a task
priority to High in SharePoint, and you do not see the changed data in Project Professional 2013.
What should you do?
A.
Use the Organizer to copy the Priority field from the SharePoint Task List.
B.
Map the Priority field from SharePoint to Project by using File, Info.
C.
Map the Priority field from SharePoint to Project by using Project, Custom Fields, Import Field.
D.
Use the Task Information box to copy the Priority field from the SharePoint Task List.
Wonderful story, reckoned we could combine several unrelated data, nevertheless truly really worth taking a appear, whoa did one discover about Mid East has got a lot more problerms too.
Sites of interest we have a link to
always a huge fan of linking to bloggers that I appreciate but really don’t get a great deal of link enjoy from
just beneath, are several absolutely not associated web sites to ours, nonetheless, they are surely really worth going over
although internet sites we backlink to below are considerably not associated to ours, we feel they are in fact really worth a go by, so possess a look
Hiya very cool web site!! Man .. Excellent .. Amazing .. I will bookmark your website and take the feeds additionally…I’m satisfied to seek out a lot of useful info here within the put up, we want work out more strategies on this regard, thanks for sharing.
http://www.GhC1uzHjyH.com/GhC1uzHjyH