You need to share and receive project plan updates dynamically with your resources

Your organization uses Project Professional 2013 and Microsoft SharePoint 2013. You are
responsible for a project with resources in different offices. All offices share the same SharePoint
intranet, and all resources have valid accounts to log into the company intranet. Your project plan
already has the correct names and assignments for each resource involved in this project. You need
to share and receive project plan updates dynamically with your resources. What should you do?

Your organization uses Project Professional 2013 and Microsoft SharePoint 2013. You are
responsible for a project with resources in different offices. All offices share the same SharePoint
intranet, and all resources have valid accounts to log into the company intranet. Your project plan
already has the correct names and assignments for each resource involved in this project. You need
to share and receive project plan updates dynamically with your resources. What should you do?

A.
Sync with SharePoint Tasks List, automatically creating a Project Site synchronized to your Project
Plan.

B.
Create the Project Site in SharePoint and upload the project plan to the project site.

C.
Create the Project Site in SharePoint and save the project plan to the project site.

D.
Copy and paste the project tasks to a SharePoint task list.



Leave a Reply 0

Your email address will not be published. Required fields are marked *