You need to provide your project’s information by using Project Professional 2013

You are a project manager who uses Microsoft Excel 2013. Your company decides to migrate all of
the current projects in Microsoft Excel 2013 to Project Professional 2013. They allow all employees
to spend 8 hours migrating each project plan. Your current and unique project plan has 462 tasks
with duration in days, and resources have been assigned and named. You have a status meeting in
two days. You need to provide your project’s information by using Project Professional 2013. What
should you do?

You are a project manager who uses Microsoft Excel 2013. Your company decides to migrate all of
the current projects in Microsoft Excel 2013 to Project Professional 2013. They allow all employees
to spend 8 hours migrating each project plan. Your current and unique project plan has 462 tasks
with duration in days, and resources have been assigned and named. You have a status meeting in
two days. You need to provide your project’s information by using Project Professional 2013. What
should you do?

A.
Create a new project plan in Project Professional 2013 and use the Gantt Chart Wizard to import
from an Excel Workbook.

B.
Rename the Excel file from .xlsx to .mpx, and open it by using Project Professional 2013, activating
the Mapping Excel Workbook feature. Map tasks, durations, and resources assigned into Microsoft
Project fields.

C.
Open the Excel File .xlsx directly from Project Professional 2013, which will convert and map tasks,
durations, and resources assigned into Project fields.

D.
Create a VBA macro by using the Excel Record Macro feature to import all tasks, durations, and
resources assigned from Excel into your new Project Professional 2013 project plan.