Which two steps should you perform?

You are a project manager who uses Project Professional 2013. You work on a software
development project, and the Project Management Office (PMO) requires you to enter project costs
associated with all work completed on your project. You receive invoices for 55,000 for software
licenses and $150 for supplies. Software licensing costs are associated with Task A: Obtain Software
License. Supply costs are associated with Task H: Project Management Administration. You need to
enter the costs into your project schedule. Which two steps should you perform? (Each correct
answer presents part of the solution. Choose two.)

You are a project manager who uses Project Professional 2013. You work on a software
development project, and the Project Management Office (PMO) requires you to enter project costs
associated with all work completed on your project. You receive invoices for 55,000 for software
licenses and $150 for supplies. Software licensing costs are associated with Task A: Obtain Software
License. Supply costs are associated with Task H: Project Management Administration. You need to
enter the costs into your project schedule. Which two steps should you perform? (Each correct
answer presents part of the solution. Choose two.)

A.
Create a cost resource for Supplies and Software License.

B.
Create a material resource for Supplies and Software License.

C.
Assign the Supply cost resource to Task H, assign the Software License cost resource to Task A,
and enter the actual costs using the Task Usage – Cost table for both Task H and A

D.
Assign the Supply material resource to Task H, assign the Software License material resource to
Task A, and enter the actual costs using the Task Usage – Cost table for both Task H and A