You are a project manager who uses Project Standard 2013. You manage a software development
project and have acquired two additional resources to assist in the completion of tasks that are on
the critical path. Both resources are also assigned to participate in other projects. Resource1 is
available 50% and Resource2 is available 75%. You need to add the resources with their availability
to the project schedule and make any allocation problems visible. What should you do?
A.
Assign the two resources to the tasks with the following units: Resource1 = 50%, Resource2 =
75%.
B.
Select the Resource Sheet and change Max Units to the following: Resource1 = 50%, Resource2 =
25%.
C.
Select the Resource Sheet and change Max Units to the following: Resource1 = 50%, Resource2 =
75%.
D.
Assign the two resources to the tasks with the following units: Resource1 = 50%, Resource2 =
25%.