Which three actions should you perform in sequence?

DROP
You are a senior project manager in a software development company. You manage your projects
with Project Professional 2013. The development team is behind schedule due to a problem found in
the architectural design of the database. The lead architect estimates that redesigning the database

will take approximately 30 hours. You create a new manual task and assign it to the lead architect.
However, the task has not been scheduled. You need to easily see a time phased view of all tasks for
the lead architect in order to schedule the task for completion. Which three actions should you
perform in sequence? (To answer, move the appropriate three actions from the list of actions to the
answer area and arrange them in the correct order.)

DROP
You are a senior project manager in a software development company. You manage your projects
with Project Professional 2013. The development team is behind schedule due to a problem found in
the architectural design of the database. The lead architect estimates that redesigning the database

will take approximately 30 hours. You create a new manual task and assign it to the lead architect.
However, the task has not been scheduled. You need to easily see a time phased view of all tasks for
the lead architect in order to schedule the task for completion. Which three actions should you
perform in sequence? (To answer, move the appropriate three actions from the list of actions to the
answer area and arrange them in the correct order.)

Answer: