You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project

You are a project manager for a large telecommunications company that uses Project Professional
2013. The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the
entire project and not for an individual task. You need to add the fixed cost of S 150,000 to your
schedule and spread it across the duration of the project. What should you do?

You are a project manager for a large telecommunications company that uses Project Professional
2013. The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the
entire project and not for an individual task. You need to add the fixed cost of S 150,000 to your
schedule and spread it across the duration of the project. What should you do?

A.
In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task
0. Change Fixed Cost Accrual to Start.

B.
In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task
0. Change Fixed Cost Accrual to Prorated.

C.
In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task
0. Change Fixed Cost Accrual to End.

D.
In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task
1. Change Fixed Cost Accrual to Start.