Which three actions should you perform in sequence?

You are a project manager who uses Project Standard 2013. Your project is approved, and you
identify named resources to replace the generic resources for your project tasks. You need to update
the project schedule to assign the named resources to their appropriate tasks. Which three actions
should you perform in sequence? (To answer, move the appropriate three actions from the list of
actions to the answer area and arrange them in the correct order.)

You are a project manager who uses Project Standard 2013. Your project is approved, and you
identify named resources to replace the generic resources for your project tasks. You need to update
the project schedule to assign the named resources to their appropriate tasks. Which three actions
should you perform in sequence? (To answer, move the appropriate three actions from the list of
actions to the answer area and arrange them in the correct order.)

Answer:

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *