You are a project manager for an organization that uses Project Professional 2013. You are planning
a project schedule that starts on March 1 and lasts four months. However, the sponsor now asks
that the project be delayed to have a finish date of December 31.
A.
Change all task constraint types to Start no later than.
B.
Change the Schedule from field to Project Finish Date.
C.
Change the project Start date so that the project will finish on December 31.
D.
Change all task constraint types to As late as possible.
E.
Change the project Finish date so that the project will finish on December 31.
??Mes coéquipiers croient en moi et je pense pouvoir les aider à gagner.
the latest nike mercurial http://www.cave-saint-antoine.fr/base.asp?solde=the-latest-nike-mercurial