What should you do?

You are a project manager and have built a project plan by using Project Professional 2013. Your
project plan has both fixed duration and fixed work tasks. You have been asked to denote key
existing tasks as milestones in the Gantt view. What should you do?

You are a project manager and have built a project plan by using Project Professional 2013. Your
project plan has both fixed duration and fixed work tasks. You have been asked to denote key
existing tasks as milestones in the Gantt view. What should you do?

A.
Format the bar styles in the Gantt view to denote the tasks as milestones.

B.
Enter the word Milestone in the Task Duration column to set the task as a milestone.

C.
Set the Duration column to 0 to set the task as a milestone.

D.
Navigate to View, Text Styles, select Milestones, and then select the black diamond.