You need to monitor this phase closely to ensure that it does not overrun

You are a project manager who uses Project Professional 2013. You are creating a project with
several phases. Your customer requires the delivery phase of the project to start on July 1 and to
finish within four weeks. The delivery phase includes a summary task, which consists of five separate
sub tasks. You need to monitor this phase closely to ensure that it does not overrun. What should
you do?

You are a project manager who uses Project Professional 2013. You are creating a project with
several phases. Your customer requires the delivery phase of the project to start on July 1 and to
finish within four weeks. The delivery phase includes a summary task, which consists of five separate
sub tasks. You need to monitor this phase closely to ensure that it does not overrun. What should
you do?

A.
Create an automatically scheduled summary task of 20 days. Set the finish date to July 29.

B.
Create a manually scheduled summary task of 20 days. Enter a Finish No Later Than constraint
which is set to July 29.

C.
Create a manually scheduled summary task of 20 days. Create a deadline for the task which is set
to July 29. Monitor the progress of the summary task against the deadline.

D.
Create an automatically scheduled summary task of 20 days. Set the start date to July 1.

E.
Set a deadline date for the automatically scheduled summary task for four weeks after July 1.
Monitor the progress of the summary task against the deadline.