You are using Microsoft Project Professional 2013. Three years ago, you successfully completed a
project to review all of the suppliers within your organization, and you have been asked to run a
similar project again. You still have the project plan from three years ago. You need to use the most
efficient method to produce a new plan with tasks based upon the old project plan. What should you
do?
A.
Rename the old plan to a .mpt file, and select it from the featured templates to create the new
project.
B.
Open the file in an earlier version of Project Professional and save it as a Project Professional 2013
file format. Open the file in Project Professional 2013.
C.
Open the file, and copy and paste the task list into the schedule.
D.
Use the New from existing project option to create the new project.