You are a project manager for a company that uses baselines in Project Standard 2013. Project
stakeholders approve an update to the baseline of a project in progress. You enter the new tasks
necessary to include the project schedule changes. You need to update the baseline for the new
tasks. What should you do?
A.
Delete the current baseline and re-baseline the entire project.
B.
Copy the current schedule to the baseline1 fields.
C.
Select the new tasks and copy the schedule to the baseline1 fields for the selected tasks.
D.
Select the new tasks and set the baseline for the selected tasks.
Explanation: