You need to view graphically which tasks and resources are causing the $5,000.00 cost variance

You manage a project schedule by using Project Professional 2013. You are concerned about project
costs. After viewing the Cost Variance column, you realize that the project has a cost variance of
55,000.00. You need to view graphically which tasks and resources are causing the $5,000.00 cost
variance. What should you do?

You manage a project schedule by using Project Professional 2013. You are concerned about project
costs. After viewing the Cost Variance column, you realize that the project has a cost variance of
55,000.00. You need to view graphically which tasks and resources are causing the $5,000.00 cost
variance. What should you do?

A.
View the Resource Graph’s Cumulative Cost view.

B.
View the Task Cost Overview report.

C.
View the Over Budget Tasks report.

D.
View the Cost Overrun report.



Leave a Reply 0

Your email address will not be published. Required fields are marked *