You need to update the schedule to reflect this change

While scheduling with Project Professional 2013 you notice that there are three days of remaining
duration on the Database Design task. The resource performing this task indicates that the work is
completed. You need to update the schedule to reflect this change. What should you do?

While scheduling with Project Professional 2013 you notice that there are three days of remaining
duration on the Database Design task. The resource performing this task indicates that the work is
completed. You need to update the schedule to reflect this change. What should you do?

A.
Enter a status date for the task.

B.
Enter 0 in remaining duration.

C.
Reschedule uncompleted work for the project schedule.

D.
Click on the task, and then click 100% complete.