What should you add to the task?

You manage a project by using Project Professional 2013. The Indicators column in the Gantt Chart
view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks
at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8
hours for the day. You need to solve this problem. What should you add to the task?

You manage a project by using Project Professional 2013. The Indicators column in the Gantt Chart
view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks
at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8
hours for the day. You need to solve this problem. What should you add to the task?

A.
A deadline

B.
A Finish to Start relationship

C.
A Finish to Finish relationship

D.
More work



Leave a Reply 0

Your email address will not be published. Required fields are marked *