You need to enter the hours in your Project Schedule on a weekly basis

You are a project manager who uses Project Professional 2013. You manage a software development
project and have baselined the project. Your Project Management Office (PMO) requires you to
capture the actual hours per resource for each task in your project schedule. You use these weekly
actual hours to generate a weekly report for your project sponsor. Your resources report their actual
hours each Friday. You need to enter the hours in your Project Schedule on a weekly basis. What
should you do?

You are a project manager who uses Project Professional 2013. You manage a software development
project and have baselined the project. Your Project Management Office (PMO) requires you to
capture the actual hours per resource for each task in your project schedule. You use these weekly
actual hours to generate a weekly report for your project sponsor. Your resources report their actual
hours each Friday. You need to enter the hours in your Project Schedule on a weekly basis. What
should you do?

A.
Choose Resource Usage view, add an Actual Work row, and enter total weekly hours per
assignment in the appropriate week.

B.
Display the Team Planner view, add an Actual Work column, and enter total weekly hours for each
task.

C.
Choose Gantt Chart view, add a Work column, and enter total weekly hours for each task.

D.
Choose Resource Form view, right-click to view Work Details, and enter total weekly hours for
each task.



Leave a Reply 0

Your email address will not be published. Required fields are marked *