What should you add to the project milestones?

You use Project Professional 2013 to manage a project that has customer-required milestone
completion dates. You need to see graphically that your milestones have slipped beyond your
customer-required dates. What should you add to the project milestones?

You use Project Professional 2013 to manage a project that has customer-required milestone
completion dates. You need to see graphically that your milestones have slipped beyond your
customer-required dates. What should you add to the project milestones?

A.
a Must finish on constraint

B.
a finish date

C.
a deadline

D.
a Finish no later than constraint