You need to correct these values before re-entering the tracking data

You manage a project by using Project Professional 2013. Your project is updated with changes to
the baseline for selected tasks. You back up your project fife before you start your next tracking
cycle. After completing the tracking cycle, you notice that the baseline duration values on some of
the summary tasks are not correct. You need to correct these values before re-entering the tracking
data. You open the backed up version of the project schedule. What should you do next?

You manage a project by using Project Professional 2013. Your project is updated with changes to
the baseline for selected tasks. You back up your project fife before you start your next tracking
cycle. After completing the tracking cycle, you notice that the baseline duration values on some of
the summary tasks are not correct. You need to correct these values before re-entering the tracking
data. You open the backed up version of the project schedule. What should you do next?

A.
Manually update the summary tasks with the new duration values.

B.
Reset the summary tasks to manual scheduling.

C.
Ensure the tasks durations are of the same denomination values. Then reenter the tracking data.

D.
Reset the baseline checking the Roll up baselines to all summary tasks option. Then reenter the
tracking data.



Leave a Reply 0

Your email address will not be published. Required fields are marked *