Your company uses Project Standard 2013 to track project progress. You need to accurately calculate
cost performance index (CPI) as a health indicator. Which three actions should you perform? (Each
correct answer presents part of the solution. Choose three.)
A.
Ensure there is a value in the Status Date field.
B.
Ensure there is a value in the Standard Rate field.
C.
Ensure Task Dependencies exist in the schedule.
D.
Enter actual progress information.
E.
Level resources within available slack.