Identify two ways that the portlet display can be organized.

The Open Requests for Resource’s portlet lists unstaffed assignments involving roles on the
selected role team. Identify two ways that the portlet display can be organized.

The Open Requests for Resource’s portlet lists unstaffed assignments involving roles on the
selected role team. Identify two ways that the portlet display can be organized.

A.
Role by Project

B.
Role by Resource

C.
Project by Role

D.
Resource by Project

E.
Resource by Role

Explanation:
This portlet has a number of customizations. The first choice to be made is to show
open assignments on all projects or just those within the filter for this dashboard. The
Organize field allows a user to define how the listed open assignments are sorted
and shown. The drop-down list offers views where open assignments are shown as:
* Roles with open assignments project by project (A)
* Projects with open assignments role by role (C)

* Roles with open assignments, sorted by project, and sub-sorted by
project codes
See figure below:

Note: The Open Requests for Resources portlet allows users to show which activities on
projects have only a role (that is, engineer) assigned and need a resource (that is, David Jackson)
assigned by their Manager.
Note 2: A variety of pre-defined portlets come with P6.